Epoxy Resin, Mica Iron Oxide, Additives, Solvents, etc. Constitute Epoxy Cloud Iron Intermediate Paint (two-component)
|
Still deciding? Get samples of $ !
Order Sample
|
| Customization: | Available |
|---|---|
| Color: | Grey |
| Appearance: | Liquid |
| Shipping Cost: | Contact the supplier about freight and estimated delivery time. |
|---|
| Payment Methods: |
|
|---|---|
| Support payments in USD |
| Secure payments: | Every payment you make on Made-in-China.com is protected by the platform. |
|---|
| Refund policy: | Claim a refund if your order doesn't ship, is missing, or arrives with product issues. |
|---|
360° Virtual Tour
Suppliers with verified business licenses
Audited by an independent third-party inspection agency
ISO9001:2015 certificate
ISO45001:2018 certificate
ISO14001
Find Similar Products
Basic Info.
- Main Raw Material
- Epoxy
- Method
- Spray
- Level
- Primer
- Drying Method
- Air Drying
- Certification
- ISO14001, CCC, RoHS, ISO9001
- Substrate
- Steel
- Components
- Film Forming Matter
- Formation Mechanism
- Conversion Type
- Luster
- Matt
- Weight
- 20kg/Barrel
- Construction Method
- High Pressure Airless Spray, Air Spray, Brush, Rol
- Coating Thickness
- Wet Film:80um Dry Film: 40um
- After Sales Service
- 5 Years
- Transport Package
- Barrel Package in Pallet
- Specification
- 35*30
- Trademark
- signal
- Origin
- Dongying China
- HS Code
- 3208100000
- Production Capacity
- 50000ton/Year
Packaging & Delivery
- Package Size
- 30.00cm * 30.00cm * 35.00cm
- Package Gross Weight
- 20.000kg
Product Description
Product Name: Epoxy resin, mica iron oxide, additives, solvents, etc. constitute epoxy cloud iron intermediate paint (two-component)
1.Introduction:
| Number of components | Two-component |
| Color | Grey |
| Proportion | About 1.20 |
| Dry Time | 23±2°C Surface dry time ≤2h, Through dry time ≤24h, Fully cured 7 days |
| Mixing ratio | 10:1.5 |
| Coating thickness | Wet film:200um Dry film: 100um |
| Construction methord | High pressure airless spray, air spray, brush, roller |
| Shelf life | 12 months |
2.Surface treatment:
When applying the primer surface, it needs to undergo secondary rust removal to achieve St3 level. If the primer is exposed to the atmosphere for a long time, all dirt such as white rust and oil stains should be removed, and the powdered paint surface should be polished off.
3.Construction conditions:
The substrate temperature must be 3°C higher than the dew point, relative humidity <85%, wind force ≤ level 3; when the substrate temperature is lower than 5°C, the epoxy resin and curing agent stop reacting and construction should be stopped. Avoid rainy, foggy, windy and sandy days and condensation in the morning and evening for outdoor construction.
4.Notes:
1. Due to the high powder content of the coating, it is recommended to use mechanical stirring to mix component A evenly before use, and then mix it evenly with component B.
2. Regularly stir during the coating process to prevent sedimentation, which can cause an imbalance between the powder to liquid ratio and affect the quality of the paint film.
3. After mixing, two-component coatings are generally used up within 5 hours, and exceeding the time limit may affect the coating quality.
4. After using the curing agent, it must be tightly covered and used up as soon as possible to prevent losses caused by reactions with water vapor in the air.
The construction process of anti-corrosion coatings typically includes key stages such as pre-construction preparation, surface treatment, coating application, and quality inspection. Below are the detailed steps:
1. Pre-Construction Preparation
-
Material Preparation:
-
Confirm the coating model and performance meet design requirements.
-
Check the shelf life and properly mix primers, intermediate coats, topcoats, and hardeners as per ratios.
-
-
Tool Preparation:
-
Prepare spraying equipment (e.g., air compressor, spray gun), brushing tools, sandpaper, grinders, masks, and gloves.
-
-
Substrate Inspection:
-
Ensure the base (metal/concrete) is flat, free of cracks, oil, or rust; repair if necessary.
-
-
Environmental Requirements:
-
Temperature: 5°C-35°C; humidity ≤85%.
-
Avoid rain, strong wind, or dusty conditions.
2. Surface Treatment
Metal Surface Treatment
-
Rust Removal:
-
Use sandblasting, shot blasting, or manual grinding to remove rust/oxidation, achieving Sa2.5 (uniform roughness) or St3 (no visible rust).
-
-
Degreasing:
-
Wipe with solvents to remove oil and dust.
-
-
Concrete Surface Treatment
-
Grinding:
-
Remove loose particles and smooth the surface; fill cracks with putty.
-
-
Drying:
-
Ensure moisture content ≤8% to prevent blistering.
3. Coating Application
-
Primer Application:
-
Apply evenly via brushing/spraying (50-80μm thickness).
-
Allow drying per manufacturer's instructions (typically >24 hours).
-
-
Intermediate Coat:
-
Apply after primer curing (e.g., fiberglass-reinforced coat) for thickness/impermeability.
-
Sand smooth post-drying.
-
-
Topcoat Application:
-
Apply 2-3 layers for weather/chemical resistance.
-
Total thickness: 200-300μm (industrial use); inspect for bubbles/voids between layers.
4. Quality Inspection & Acceptance
-
Visual Check:
-
Coating must be smooth, free of sagging, cracks, or pinholes; color uniformity required.
-
-
Thickness Test:
-
Use a thickness gauge (3+ random checks per ten squre meter; ≥90% compliance).
-
-
Adhesion Test:
-
Cross-cut test: No peeling = pass.
-
-
Spark Test:
-
Use a holiday detector to locate coating defects; repair if leaks found.
-
-
-
-


1. Why Choose Shandong Judong New Materials?
We leverage our full industrial chain integration, rich overseas project experience, superior product stability, and competitive pricing to offer one-stop solutions covering R&D, production, and construction. Whether for large-scale long-term cooperation or urgent small-batch orders, we meet your needs to help you stand out in market competition.
2.What's your MOQ (min order quantity),production period and delivery time?
Our MOQ is 100Kg. We accept mixed order and the production period and delivery time are 7-14 days.
3.Which industries and applications do you serve?
Key sectors include bridges, petrochemical, power facilities, machinery, marine engineering, and industrial manufacturing.
4.Can I have my logo on the package?
Of course! Customized logo, customized packaging and graphic customization are available.
Yes, we can offer you this sample for free, but the shipment charge usually paid by your
side, please advise your express account and address in details. Thanks.
Send your message to this supplier
People who viewed this also viewed
Product Groups
Find Similar Products By Category
- Supplier Homepage
- Products
- Anti-Corrosion Coatings
- Petrochemical Industry
- Epoxy Resin, Mica Iron Oxide, Additives, Solvents, etc. Constitute Epoxy Cloud Iron Intermediate Paint (two-component)